Construction of inter-settlement gas pipeline “Glazov – Krasnogorsk village, Krasnogorsk District, Udmurt Republic”

行业: Production and distribution of electricity, gas and water

实施阶段: Pre-investment stage

该项目的目的:

Construction of high pressure gas pipeline to supply natural gas to Krasnogorsk district citizens; creating a more comfortable living conditions for citizens; cost reduction of thermal energy for boiler, which is working on solid fuel now; improving the environmental situation in the region.

项目说明:

Construction of high pressure gas pipeline on the territory of the Glazov and Krasnogorsk districts with total length of 65,445 meters, including 33200 m in the Krasnogorsk district

总费用:

180 万。

项目持续时间:

2013 - 2015

整体指标:

Making the connection to the natural gas production facilities in 8 settlements around Krasnogorsk district (Villages: Deby, Udm.Karaul, Zotovo, Tuktash, St.Kachkashur, Elovo, St. Kenovay, Artik)

作者

Administration of municipality "Krasnogorsk district"

代表

Sigova Tamara

地址

427650, Udmurt Republic, Krasnogorsk village, Lenin Str., 64

电话

8 (34164) 2-16-00; 2-12-31; krasno2@udm.net

我们的合作伙伴

谢谢你!

我们会给你回电话一个小时内